Schedule Report

The Schedule Report is a resource report that displays scheduled hours for resources by month or week broken down by Project or Workspace.

  • This report will include any current, future or historical schedules for resources.
  • This means the results may include schedules for active and inactive users.

Viewing the Schedule Report

This report appears in both the Analysis and Resource Management applications.

To view this report in Analysis:

  1. In the Work Management Toolbar, click View Applications.
  2. Click the Analysis application tile.
  3. Under the Resource Reports section of the navigation menu, click Schedule Report.
  4.  

To view this report in Resource Management:

  1. In the Work Management Toolbar, click View Applications.
  2. Click the Resource Management application tile.
  3. Under the Standard Reports section of the navigation menu, click Schedule Report.
100% helpful - 1 review