This article is written for individuals who will be reporting on plan tasks in the TeamDynamix system. They will need to have access to TDNext, as well as access to the Project/Workspaces application.
Overview
The report displays the progress metrics for each plan within a project or all the project plans in the system. Only active projects are included in this report.
Where to Find This
This feature appears in TDNext in the Project/Workspaces application. It will be located within the navigation on the left side of the screen.
Navigate to this report following this path:
- TDNext > Project/Workspaces > Standard Plan Reports
Using the Tasks Summary By Plan Report
The details shown for each project plan include:
- Start - Start date (earliest task start date)
- End - End date (latest task end date)
- Tasks -Total number of tasks
- Clsd - Number of closed tasks
- Clsd % - Percentage of closed tasks to total tasks
- Opn - Number of open tasks
- Opn % - Percentage of open tasks to total tasks
- Est Hrs - Total estimated hours
- Act Hrs - Total hours of time reported against tasks on this plan
- +- Hrs - Hours over/under the estimate
- % Wrkd - Percent of hours worked
- MS - Number of milestones
- MS % Comp - Number of milestones complete
- Est % Comp - Estimated percent complete of all tasks
- % Days Used - Percent of days used
Calculations
- Clsd % = (Closed Tasks) / (Total Tasks)
- Opn % = (Open Tasks) / (Total Tasks)
- +- Hrs = (Estimated Hours) - (Actual Hours)
- % Wrkd = (Actual Hours) / (Estimated Hours)