Tasks Summary By Plan Report

Overview

The report displays the progress metrics for each plan within a project or all the project plans in the system. Only active projects are included in this report.

Where to Find This

This feature appears in TDNext in the Project/Workspaces application. It will be located within the navigation on the left side of the screen.

Navigate to this report following this path:

  • TDNext > Project/Workspaces  > Standard Plan Reports

Using the Tasks Summary By Plan Report

The details shown for each project plan include:

  • Start - Start date (earliest task start date)
  • End - End date (latest task end date)
  • Tasks -Total number of tasks
  • Clsd - Number of closed tasks
  • Clsd % - Percentage of closed tasks to total tasks
  • Opn - Number of open tasks
  • Opn % - Percentage of open tasks to total tasks
  • Est Hrs - Total estimated hours
  • Act Hrs - Total hours of time reported against tasks on this plan
  • +- Hrs - Hours over/under the estimate
  • % Wrkd - Percent of hours worked
  • MS - Number of milestones
  • MS % Comp - Number of milestones complete
  • Est % Comp - Estimated percent complete of all tasks
  • % Days Used - Percent of days used

Calculations

  • Clsd % = (Closed Tasks) / (Total Tasks)
  • Opn % = (Open Tasks) / (Total Tasks)
  • +- Hrs = (Estimated Hours) - (Actual Hours)
  • % Wrkd = (Actual Hours) / (Estimated Hours)