Tasks Summary By Plan Report

The Tasks Summary By Plan Report is a Projects Application report that displays progress metrics for project plans.

  • Only active projects are included in this report.

Viewing the Tasks Summary By Plan Report

To view this report:

  1. In the Work Management Toolbar, click View Applications.
  2. Click the Projects application tile.
  3. Under the Standard Plan Reports section of the navigation menu, click Tasks Summary By Plan Report.
  4. (OPTIONAL) Select a specific Project to report on.
    • By default, the report runs for All projects.
  5. Click Run Report.

You'll see the following info for each project plan:

  • Plan: Plan name
  • Start: Start date (earliest task start date)
  • End: End date (latest task end date)
  • Tasks: Total number of tasks
  • Clsd: Number of closed tasks
  • Clsd %: Percentage of closed tasks to total tasks
  • Opn: Number of open tasks
  • Opn %: Percentage of open tasks to total tasks
  • Est Hrs: Total estimated hours
  • Act Hrs: Total hours of time reported against tasks on this plan
  • +- Hrs: Hours over/under the estimate
  • % Wrkd: Percent of hours worked
  • MS: Number of milestones
  • MS % Comp: Number of milestones complete
  • Est % Comp: Estimated percent complete of all tasks
  • % Days Used: Percent of days used

Calculations

  • Clsd % = (Closed Tasks) / (Total Tasks)
  • Opn % = (Open Tasks) / (Total Tasks)
  • +- Hrs = (Estimated Hours) - (Actual Hours)
  • % Wrkd = (Actual Hours) / (Estimated Hours)