Project Status Report

The Project Status Report is a Projects Application report that provides a project management status report for the selected Project/Workspace.

Viewing the Project Status Report

To view this report:

  1. In the Work Management Toolbar, click View Applications.
  2. Click the Projects application tile.
  3. Under the Status Reports section of the navigation menu, click Project Status Report.
  4. Enter the time frame in the Date fields.
  5. Select the Project/Workspace you want to run the report on.
  6. (OPTIONAL) Add Report Comments.
  7. (OPTIONAL) Change which items will be included.
    • Milestones (Completed or that should have been completed for the period)
    • Tasks Completed (During the period)
    • Active Tasks (Tasks started before the period end date that are not complete)
    • Overdue Tasks (Tasks whose end date is before today and the percent complete is less than 100%)
    • Events (During the period)
    • Upcoming Events (In the next 7 Calendar days)
    • Time Reported By Project (During the period)
    • Open Issues
    • Closed Issues (During the period)
    • Open Risks
    • Closed Risks (During the period)
  8. Click Run Report.