Pull Actual Hours By Task on a Project
Hello, is there a way to pull actual hours on a project by task?
Asked by Rachel Renckly
on Fri 8/16/24 11:21 AM
Sign In to leave feedback or contribute an answer
Answer (1)
This answer has been marked as the accepted answer
Brittany Renn
Fri 8/16/24 11:49 AM
Hi Rachel,
You should be able to report on Actual Hours for a Tasks by going to TDNext > Analysis > +New > Actual Hours Report and form there, you can filter on Item Type is one of Task and Project/Workspace ID, if you're only wanting to look at a specific project.
Best,
Brittany Renn
TDX Support
No feedback
Thank you! I think this will give them what they are looking for.
- Rachel Renckly