Project Duration

Hi 

In Project >> General details, there are 3 fields - Start Date, End Date and Duration.  I'm unable to figure out how Duration is being calculated. I used TimeAndDate.com to try and figure out out - accounting for weekends, holidays, etc, but I couldn't get it to match.  Any ideas on how it's being calculated?

Example 1
Start Date 5/15/2024
End Date 7/30/2024
Duration = 55

Example 2
Start Date 2/23/2022 
End Date 2/2/2024
Duration = 491


 

 

 

Tags projects duration
Asked by Kimberly Clapp on Fri 6/7/24 2:42 PM
Sign In to leave feedback or contribute an answer

Answer (1)

This answer has been marked as the accepted answer
Brittany Renn Fri 6/7/24 2:59 PM

Hi Kimberly, 

Project Duration should show the number of weekdays in the project excluding days off.

Best,
Brittany Renn
TDX Support

No feedback
Can you elaborate on what is meant by 'days off' ? I tried to calculate this with and without weekends and holidays, but it still didn't quite match up. - Kimberly Clapp Sat 6/8/24 5:57 AM
Days off would reference any entries you have created in TDAdmin > Organization Settings > Days Off. - Brittany Renn Mon 6/10/24 10:05 AM