Project Initial Hours Calculation
Hi,
Can you explain how the "initial hours" field in projects and project reporting are calculated?
Thanks
Asked by Kim Rathbone
on Wed 1/17/24 2:48 PM
Sign In to leave feedback or contribute an answer
Answer (1)
This answer has been marked as the accepted answer
Brittany Renn
Wed 1/17/24 4:27 PM
Hi Kim,
The Initial Hours should represent the Total Estimated Hours that were entered when the project was created or the sum of the role forecasts when the project was staffed.
Let me know if you have further questions.
Best,
Brittany Renn
TDX Support