TD project plan % complete inaccurate

I have a project plan that has in several in progress tasks that are less than 100% complete. However, the overall plan % complete is showing as 100%. I have tried checking the plan out and checking it back in hoping that would fix it, but no luck. Any ideas what the issue is?

Tags plan projectplan
Asked by Tracey Davis on Tue 8/15/23 10:34 AM Last edited Tue 8/15/23 10:34 AM
Sign In to leave feedback or contribute an answer

Answer (1)

This answer has been marked as the accepted answer
Mark Sayers Tue 8/15/23 10:43 AM

Hi Tracey,

Do any of the tasks on that plan have Estimated Hours? Because if so the calculation changes for plan percent complete, per this KB: https://solutions.teamdynamix.com/TDClient/1965/Portal/KB/ArticleDet?ID=8127

Sincerely,
Mark Sayers
Sr Support Consultant, CS

No feedback