I have a need to report on project request turn-around-time (age from submission to decision (approved/declined/withdrawn). In looking at the Portfolio Planning report parameters, I don't see a way to do this. Do you have any recommendations?
Answer (1)
Hi Rebecca,
If you create a Project Request Report, you should be able to pull in the Start and End Dates on the Report. If you didn't want to report on it that way, you can also include the 'Created' column, which would offer the date the request was created and then another field for 'Approved' to see the date it was approved. There isn't currently a reporting feature for declined/withdrawn, but you can add a column for 'Status' and 'Status' date if you wanted to see all statuses.
Best,
Brittany Renn
TDX Support