Using mixed time units in project plans
Is it possible to use .5 days or 4 hours in a project plan while other task durations are in days?
Asked by Peter Abashian
on Wed 2/22/23 7:27 AM
Sign In to leave feedback or contribute an answer
Answer (1)
This answer has been marked as the accepted answer
Mark Sayers
Wed 2/22/23 9:05 AM
Last edited Wed 2/22/23 9:05 AM
Hello Peter,
The duration value stems from the count of days from the start date and end date columns for a particular row. The minimum number it can display is 1 day, ie a start date that is the same as the end date.
Sincerely,
Mark Sayers
Sr Support Consultant, CS