Link Multiple Plan Tasks to an Issue?
Hi -
Is it possible to link one Project Issue to multiple Tasks in a Plan?
Asked by Sara Ainsworth
on Tue 12/27/22 11:34 AM
Sign In to leave feedback or contribute an answer
Answer (1)
This answer has been marked as the accepted answer
Mark Sayers
Tue 12/27/22 11:52 AM
Hello Sara,
Unfortunately at this time you can only associate an Issue with one project Task at a time, mainly because to do so you have to create the Issue *from* the project task in question.