Move Task to a Different Plan?
Is there a way to move a Project Task to a different Plan within the same Project (both are waterfall)? I'm trying to consolidate them and a couple of Tasks have recorded hours and updates.
Asked by Sara Ainsworth
on Fri 10/14/22 10:59 AM
Sign In to leave feedback or contribute an answer
Answer (1)
This answer has been marked as the accepted answer
Mark Sayers
Mon 10/17/22 9:24 AM
Hello Sara,
Unforutnately waterfall plan tasks just are not able to be moved between waterfall plans.
You could submit this as an enhancement request if you wish though: https://solutions.teamdynamix.com/TDClient/1965/Portal/Requests/ServiceDet?ID=2148
Sincerely,
Mark Sayers
Sr Support Consultant, CS