Project Status percentage does not reflect Project Plan completion

The project plan shows we are more than 3/4 of the way through the project.
The pie chart says it is 88%, but the project status indicator in the project list shows 0%.
Did I not configure something correctly?
They should all show the...
2 Answers
Timothy Mellin Last activity on 9/3/2024 6:48:17 PM by Timothy Mellin

Project appears 100% complete, but there are still open tasks

Hello, I'm wondering why my total % complete says 100% when I clearly still have tasks which have not been completed. Screen shot is below.
1 Answer
Sarah Glatz Last activity on 9/25/2023 9:24:07 AM by Mark Sayers