Project Plan task dependencies where both tasks can be completed the same day
I have these two lines on my project plan
34 run process X 6/7 - 6/10
35 run process Y 6/7 - 6/10
Step 34 must complete before we can do step 35. They only take 5 minutes so they can be done on the sa...
34 run process X 6/7 - 6/10
35 run process Y 6/7 - 6/10
Step 34 must complete before we can do step 35. They only take 5 minutes so they can be done on the sa...
1 Answer
Carolyn Jensen
Last activity on 6/7/2023 3:54:20 PM by Mark Sayers