% complete not tallying in Plans
The overall percentage complete is not rolling up in my project template under Plans. It is in the subheader, but not at the top of the page.
Has anyone else had this problem? Any suggestions to fix it?
Asked by Tracey Napolitano
on Wed 3/29/23 1:09 PM
Sign In to leave feedback or contribute an answer
Answer (1)
This answer has been marked as the accepted answer
Mark Sayers
Wed 3/29/23 1:35 PM
Hello Tracey,
Are you utilizing Estimated Hours on the tasks in your plan there?
If so, the percent complete calculation changes to include whether or not there are actual hours logged against the tasks with Estimated Hours, and if those actual hours meet (or not) the specified number of Estimated Hours. This is more specifically mentioned in this KB in the "Parent Tasks" and "Plans" sections: https://solutions.teamdynamix.com/TDClient/1965/Portal/KB/ArticleDet?ID=8127
Sincerely,
Mark Sayers
Sr Support Consultant, CS