Assigning Resource Pool to a project request
How do I assign a resource pool to a project request? I believe I used to be able to do this.
Answers (2)
Hi Barrie,
I see what you are saying now. We actually changed this for 9.3 to allow for the new request collaboration features (reference 9.3 release notes here). The Resources tab controls which people can work on the request while it is in the Requested stage. The place to configure functional role forecasts on a project request as you did before is now called Role Forecasts. Let me know if you are able to add your functional role forecasts properly there.
I hope this helps clear up any confusion. If you have any further questions, please let me know.
Sincerely,
Mark Sayers
TeamDynamix
Hi Barrie,
A resource pool as a whole is not something that can be added on a project request. Resources are only able to be added individually because they could possibly come from different resource pools.
I hope this has answered your question. If you have any further questions or concerns, please let me know.
Sincerely,
Mark Sayers
TeamDynamix