Negative hours and cannot check the Notification box

What are "Unscheduled hours" here (-203.20)? The capacity of this person by month when they are added to the project appears to be a positive number.

Tags project-management Resource-Management scheduling capacity unscheduled-hours
Asked by Andy Novak on Thu 3/10/16 10:16 AM
Sign In to leave feedback or contribute an answer

Answer (1)

This answer has been marked as the accepted answer
Jamey Stock Thu 3/10/16 10:24 AM

Hi Andy,

After looking into this, the Unscheduled Hours field displays the Estimated Hours for the project subtracted by the amount of assigned hours for the resource. It seems that the user has been added to a project where Assigned Hours is 203.2 greater than the Estimated Hours.

If you find that this is not working properly, please provide screenshots of the project's estimated hours and the resource schedule and we will be happy to investigate further. Please let us know if there is anything else we can do for you.

Sincerely,
Jamey Stock
TeamDynamix

No feedback