Display of Accrued Project Time
I am working to reconcile and close out a project and have a question about how accrued time is being displayed. Attachment Capture1.png is a T&E report on my project that shows 5808.53 hours with an amount of $275,943.75. Attachment Capture2.png is screenshot of the Project Detail screen for my project. It displays my budget for time and hours and shows that I have accrued 5808.53 hours. However, it show that I have accrued $0 for these hours.
Is this a bug in the Project Detail screen or could I be doing something wrong with the logging of hours that is preventing the budget from being accrued?
Asked by Ken McCrery
on Mon 6/15/15 11:10 AM
Sign In to leave feedback or contribute an answer
Answer (1)
Aaron Crane
Fri 6/19/15 2:17 PM
Hi Ken,
I'm looking into this. Let me log something with our Engineering group and then I'll get back to you.
Aaron
1 of 1 users found this helpful.