Resource Removal

Hi Drake,
If a resource is removed from the project and the schedule is delegate to other project resource.
Will this action sum the schedule hours to the resource for which the hours have been delegated?
Thanks for clarifying.

Tags Resource-Management project-management delegation
Asked by Carmen Villen Puerto on Fri 10/10/14 1:18 PM
Sign In to leave feedback or contribute an answer

Answer (1)

Drake Sigler Fri 10/10/14 1:22 PM

Hi Carmen,

If you delegate the items associated to a resource when removing that resource, the schedules will not be delegated, only the items (files, issues, tasks, etc.) If your project is manage by plan, the schedules will be updated for the resource who received all the tasks from the removed resource the next time those schedules are updated.

I hope this helps!