I have a question. Okay, maybe two.

What does it mean when tasks are highlighted in green? Also, if you hover over the little person icon, it says that the task shows in My Work. However, the task is assigned to someone else and really doesn't appear in My Work. 

Tags mywork my-work PPM projects tasks
Asked by Matt Sayers on Thu 9/11/14 5:23 PM Last edited Wed 3/25/15 11:04 AM
Sign In to leave feedback or contribute an answer

Answer (1)

This answer has been marked as the accepted answer
Matt Sayers Thu 9/11/14 5:23 PM Last edited Thu 9/11/14 5:23 PM

A task is highlighted in green and given the little person icon when the task is in anyone's "My Work" list, not just yours. This indicates that someone is actively working on the task.

1 of 1 users found this helpful.