How do I activate a Plan?

I have a project with 2 plans. One plan is inactive. How to I make it active? Importing a new plan did not work as a work around, as it is inactive also.

Tags project-plans
Asked by Vicki Gutierrez on Tue 8/26/14 11:15 AM Last edited Tue 8/26/14 2:29 PM
Sign In to leave feedback or contribute an answer

Answer (1)

Drake Sigler Tue 8/26/14 11:15 AM Last edited Tue 8/26/14 2:29 PM

"Inactive" when referring to plans simply means that the dates are in the past. If a plan does not have any tasks with an end date later than today, the plan will show as inactive.

To reactivate a plan, simply extend its end date to beyond today.

0 of 1 users found this helpful.