Plan Shift Question

Is there any functionality that allows to postpone some tasks for example one month after the current set date? For example move (parent tasks + children tasks) from one month (May) to another (June).

Tags Plan-Manager
Asked by Carmen Villen Puerto on Fri 8/22/14 2:08 PM Last edited Fri 8/22/14 3:11 PM
Sign In to leave feedback or contribute an answer

Answers (2)

Jamey Stock Fri 8/22/14 2:10 PM

Hi Carmen,

We have a "Shift" feature available from the "Details" tab of the project plan. You can move all the dates of a plan forward or backward by a specified number of work days. Shifting the plan will shift all non-completed tasks on the plan.

1 of 1 users found this helpful.

Heidi Wilhelm Mon 8/8/16 3:25 PM Last edited Mon 8/8/16 3:27 PM

Where is this function with the newest update - 9.4?

The Plan Details window doesn't seem to be editable.

No feedback