Adding an Alternate Project Manager
Body
Question
How can I add an alternate manager to a project?
Environment
Project Management
Answer
- Within a project, select Resources from the left navigation menu
- Ensure that the user is listed as a Resource on the project. (Article - Working with Project Resources)
- From the Actions drop down choose Change Manager
- Select the check box next to the user(s) that you would like to make Alternate Managers
- Save
Additional Information
- Only a the main Project Manager on a project can add additional users as Alternate Managers.
- Users must have access to TDNext and the Projects application to be added as an Alternate Manager.
Details