Adding an Alternate Project Manager

Body

Question

How can I add an alternate manager to a project?

Environment

  • Work Management (TDNext) > Project application

Answer

  1. Within a project, select Resources from the left navigation menu
  2. Ensure that the user is listed as a Resource on the project. (Article - Working with Project Resources)
  3. From the Actions dropdown choose Change Manager
  4. Select the check box next to the user(s) that you would like to make Alternate Managers
  5. Save

Additional Information

  • Only the main Project Manager on a project can add additional users as Alternate Managers.
  • Users must have access to Work Manage and the specific Projects application to be added as an Alternate Manager. 

Details

Details

Article ID: 164106
Created
Tue 1/28/25 2:30 PM
Modified
Mon 5/18/26 10:50 AM