Determining A Task Variance

In order to view task variance, the user must:

  1. Go to the task list for the appropriate iteration/plan in Iteration/Plan Manager.
  2. View a task variance in the task list column named "Baseline Variance". The variance will be expressed in days early or late as compared to the original start-date and end-date estimates. You may need to add this column to the columns visible.

Note that a project iteration/plan must have an active baseline to show variance.