Adding Project Milestone Tasks

To create a project milestone, the user must:

  1. Go to the task list for the appropriate iteration/plan in Iteration/Plan Manager.
  2. Right-click on the task, hover your mouse over Milestone and select "Set as Milestone".
  3. Alternatively, you can select the task by clicking the row number cell then choose Milestone > Mark as Milestone from the ribbon bar.

    OR

  1. Go to the task list for the appropriate iteration/plan in Iteration/Plan Manager.
  2. Open the task detail dialog window by double-clicking the task row for the task you want to make a milestone.
  3. Edit the task by clicking the "Edit" button.
  4. Check the "Milestone" checkbox.
  5. Click the "Save" button.