I Have Allocated Resources To My Project Through A Project Plan. However, When I Run A "Resource Allocation" Report, My Changes Are Not Reflected

When a project is set to manage resource allocation by project plan(s), additions, changes, and deletions of resources do not take effect immediately. Therefore, the changes do not show up in resource allocation reports. These changes are updated by TeamDynamix in batches every night.

You can update your changes manually to more quickly reflect changes in resource allocation by entering the Management console, select the appropriate project name link, then click the "Resources" tab. Click on the "Update Schedules" button. This will apply any resource allocation changes. If you run a resource allocation report now, the correct resource allocation will display.