Scheduled Hours

Knowing that Available Hours = (Available Workable Hours) - (Scheduled Hours for the period), Does teamdynamix consider scheduled hours the sum of time scheduled in projects and time scheduled in workspaces only?
In our organization, resource...
1 Answer
Peggy B Last activity on 3/2/2020 12:05:32 PM by Mark Sayers

Availability Management and Leave Time

To TeamDynamix Support:

While testing availability management in TDX today, we noticed a person's availability went negative for a week when they took a 40 hour leave during the same week.

Specifically, their daily capacity on their use...
6 Answers
Burr Watters Last activity on 9/16/2016 1:24:42 PM by Burr Watters

Remaining Hours vs Scheduled Hours

Hello,

1. I have a project, managed by plan, where % complete is by remaining hours

2. I create a task which starts on September 1st and ends on September 15th, add estimated hours of 40, and then assign John as a resource

3...
1 Answer
Andrew Lutzuk Last activity on 8/28/2015 10:59:46 AM by Phil Curl

ACTION: Availability Report Bug

The 8.6 Availability Report does not show "All Tickets", and this makes it impossible to accurately see the availability of resources and schedule realistically.
1 Answer